Contractor's working schedule
Some construction contracts, in particular in the USA, require that the contractor produces a contractor’s working schedule. This is a critical path method (CPM) logic diagram used by the contractor, not only to plan the works, but also to record actual progress and to show how the remaining works will be completed. This is not a static schedule but is maintained by the contractor throughout the duration of the works and published periodically as a form of reporting.
In the UK, the Chartered Institute of Building’s (CIOB) Contract for Complex Projects (CPC 2013), requires that the contractor produces a working schedule, (sometimes referred to as the contractor’s working schedule) which CIOB describe as ‘a resource and cost-loaded critical path network’.
The working schedule is a digital, quality-controlled, critical path network, used to manage time, and updated with progress data such that it automatically calculates the construction end date for the works.
Cost management is carried out by reference to values attributed to the activities in the schedule, such that the schedule constantly calculates the value of work done to date and predicts the out-turn cost of the works. Payment is based upon work properly done according to the working schedule.
CIOB suggest that the working schedule is prepared at three levels of density. At low and medium density, activity durations may be estimated and linked with activity-related logic. At high density (the short-term look ahead) activity durations are calculated by reference to resources and achievable productivity and linked by resource and location-related logic.
NB In November 2015, the Complex Projects Contract was updated and renamed the Time and Cost Management Contract.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Chartered Institute of Building.
- Construction contractor.
- Contract for Complex Projects
- Contractor’s master programme.
- Milestones.
- Noise nuisance.
- Programme.
- Schedule.
- Schedule of work.
- Scheduling construction activities.
- Time management of construction projects.
- Time and Cost Management Contract.
- What hours are construction sites allowed to operate?
- Workmanship in construction.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.